The tub goes in before the wall around it. How a Playa Vista fire rebuild is sequenced, from framing through finishes, with an itemized quote.
Bulky and awkward things go into a Playa Vista rebuild before anything closes around them. A cast-iron tub, a steel beam, a stair stringer and a main duct trunk will not fit through a finished doorway, so they are set while the framing is still open. Planning that sequence on paper, room by room, keeps the trades from tearing out finished work to fit one big piece.
Big pieces before closed walls
We list every large item in a rebuild and mark the stage when it must arrive. Beams and posts come in with the frame. Tubs and shower bases are set on their drains before the surrounding studs are boxed in. A staircase is framed before the floor above it is sheathed, so the stringers can be lowered into position. The main duct trunks run through the joists before ceilings are hung. Each item gets a line in the schedule, which the site lead checks off before the next trade starts.
Inspections gate the closing
Inspectors need to see framing, plumbing, electrical and mechanical work before it disappears. That is the reason closing happens in a fixed order. Rough plumbing and electrical go in, then the city inspects, then insulation, then drywall, then a nailing check on the drywall, and only then do taping and paint begin. If an inspector wants a change, the walls are still open, so the fix takes an afternoon and no demolition is involved. A closing that follows the inspections is also the one that goes fastest overall.
About fire rebuild & reconstructionEverything we do in Playa Vista
Fire Rebuild & Reconstruction in Playa Vista: what families ask
A bedroom can be built into the new plan when the lot has room for it. Adding area changes what the building department reviews, so we check height and setbacks first. We then draw the new room, including where its door, window and closet go, so you can judge it before the set is filed.
Nothing is framed until the paper is done. Debris is hauled off, a surveyor measures the lot and the plans you saved get read. The structural and energy sheets are drawn, the building department receives the set, and reviewer comments are answered. When the permit is issued, the order of work on site begins.
Lines in the quote follow the order of work on site. Items that have to be set early, such as beams and stair framing, are broken out with their own prices. Put it next to your insurance claim and you can match each line to a loss. We do not speak for the carrier on coverage.
Fire Rebuild & Reconstruction in other cities
Other projects we take on in Playa Vista
Your Playa Vista project, start to finish
Tell us about the house and the space you need. We reply by phone or email to plan a visit.